Construction Progress January 2017

Things continue to move along on the construction site.

The contractor continues to work on enclosing all of the floors, and installing the necessary mechanical and electrical infrastructure for the new OAG. The concrete work for the public sector and the structural steel installation, with the exception of the Black Box catwalks and travelling beams, has been completed. The 3rd condo floor (19 of 23) of the tower was completed in December and floor 20 was poured earlier this month. The concrete topping for the OAG north and south roof-top terraces is expected to be poured during the week of January 16 – 20, weather dependent.